Week 1–2
Site Preparation
- Utility locating
- Temporary fencing
- Dust protection
- Dumpster delivery
- Material staging
Week 2–3
Demolition
Workers remove:
- Existing siding
- Roof sections
- Windows
- Walls
- Concrete (if required)
Only the areas needed for the addition are removed.
Week 3–5
Excavation
Heavy equipment digs for:
- Footings
- Foundation walls
- Utility connections
The site is graded and prepared.
Week 5–6
Footings
Crews install:
- Rebar
- Concrete footings
- Anchor bolts
County Inspection
The county inspects the footings before additional work continues.
Week 6–8
Foundation
Construction includes:
- Concrete foundation walls
- Waterproofing
- Drain tile
- Gravel
- Backfill
Inspection
The foundation is inspected before framing.
Week 8–12
Framing
The structure is built, including:
- Floors
- Walls
- Roof
- Beams
- Headers
- Trusses
- Sheathing
The house now takes its final shape.
Week 12–14
Roofing
Installation includes:
- Underlayment
- Flashing
- Roofing shingles
- Ridge vents
The structure becomes weather resistant.
Week 13–15
Windows & Exterior Doors
Workers install:
- Windows
- Entry doors
- Patio doors
The building is dried in and protected from weather.
Week 14–18
Rough Plumbing
Installation includes:
- Water lines
- Drain lines
- Vent piping
- Gas piping
Week 14–18
Rough Electrical
Electricians install:
- Wiring
- Breaker panels
- Switches
- Receptacles
- Smoke detectors
Week 14–18
Rough HVAC
Installation includes:
- Ductwork
- Returns
- Supply vents
- HVAC equipment
County Rough Inspection
Inspectors review:
- Framing
- Plumbing
- Electrical
- Mechanical
Any required corrections are completed before insulation.
Week 18–19
Insulation
Walls and ceilings receive insulation to meet energy code requirements.
County Insulation Inspection
Approval is required before drywall installation.
Week 19–22
Drywall
Workers:
- Hang drywall
- Tape joints
- Apply multiple coats of compound
- Sand surfaces
- Prime walls
Week 22–28
Interior Finishes
Installation includes:
- Interior doors
- Trim
- Baseboards
- Crown molding
- Cabinets
- Tile
- Hardwood flooring
- Painting
- Countertops
Week 26–30
Finish Trades
Final installation includes:
- Plumbing fixtures
- Light fixtures
- Appliances
- HVAC registers
- Bathroom accessories
Week 30–32
Exterior Work
Crews complete:
- Siding
- Brick or stone
- Gutters
- Downspouts
- Driveway repairs
- Landscaping
- Walkways